Hamptons Facade
I have been very slack in providing you with updates on our new build’s progress. Mostly, I share pics on Instagram, so make sure you’re following me there if you want to see all the action. I am pleased to report that we are getting CLOSE to completion. While we were hoping that we would be in before the start of this year, realistically that was always a long shot. Today, we move out of our rental and into temporary accomodation. We’ll be moving around like gypsies until our house is finished. At this stage we are hoping for early-mid February handover. Keep your fingers crossed for us!

Ready for action!
New house update
So, let’s take a look at where this all began.
November 2016 – We bought a knock-down in the suburb we wanted to stay in
December 2016 – Engaged Porter Davis to build our home. Decided on House.
January 2017 – Visited World of Style to make all our selections. Read here
February 2017 – Contract negotiation
March 2017 – House knocked down
April 2017 – Officially signed building contract
May 2017 –
June 2017 – Pop the champagne. The Cement slab is POURED!
July 2017 – Present – Build is underway
Here is how it’s shaping up:

Mood Board Inspo!

The slab is poured and framing is underway.

The exterior is complete and now it’s time for fit out.

Internal staircase, which will be painted and have a carpet runner.

Powder room is almost complete

Upstairs ensuite with double vanity

The kitchen is getting close!

Colour scheme of white and grey in kitchen

We chose a stone bench top with a faint marble vein.